Wilton Gas Metering Station
CE Group was engaged by Jemena to provide the electrical installation for a new natural gas metering station located in Wilton, NSW.
The new metering facility was the final stage in the Eastern Gas Pipeline project for Jemena and supplied natural gas to approximately 1/3rd of Sydney’s gas customers. This involved constructing the new metering facility to provide gas to two existing metering facilities in the area.
APLNG Curtis Island Permanent Buildings
CE Group, an experienced electrical mining contractor, was contracted by Leighton Contractors to deliver electrical services for 10 permanent buildings at the Australia Pacific LNG (APLNG) project.
SAG Ball Feeder Mill, Lihir
Located in the New Ireland Province of Lihir in Papua New Guinea, CE Group executed Electrical and Instrumentation works on the Semi Autogenous Grinding Mill’s Ball Feeder project.
This project automated the addition of grinding media to the HGO1, HGO2 & FGO SAG mills to enable a consistent ball charge to be maintained within each mill, maximising grinding circuit throughput and ultimately increasing efficiency of the operation. In conjunction with risk reduction in manual handling labour, the project introduced innovations and technology not seen in the region, and continued rollout of initiatives from other Newcrest mine sites.
BMA Goonyella Horizontal Belt Filter Installation
Goonyella Riverside Coal Handling Preparation Plant upgrade involved the upgrade of three conveyor drives, motor control centre extension and installation of the 4th belt filter.
Goonyella Riverside Mine is a large open cut coking coal mine in the Bowen Basin. The coal is well known for its great coking characteristics. Much of the coal was such a high grade, the wash plants were often programmed to add ash to meet the contracted export quality targets.
GRM Coal Reclaimer and Stacker Upgrade
Goonyella Riverside Mine (GRM) is a coal mine located in the Bowen Basin approximately 30km north of Moranbah, and 190km southwest of Mackay. The Raw Coal Reclaimer and Raw Coal Stacker at Goonyella Riverside Mine is over 30 years old and much of both machines do not meet latest Standards, Codes and BMA specifications. In effort to rectify this and extend the machines’ operational life, the machines were to undergo an overhaul of electrical and mechanical infrastructure.
The project required significant works during the shutdown. The scope of work encompassed all E&I activities and Mechanical rectification on both machines, which included the following:
- Replace existing switchrooms including temporary works to allow removal
- Replace travel motors, remove existing travel brakes and replace isolators and cabling
- Re-connect existing cables to new switchrooms
- Provide modification to platforms and handrails to accommodate new switchrooms
- Testing and quality assurance
- Provide assistance for commissioning
Ichthys Onshore Operating Facility
CE Groups Managed Services team was deployed to assist Veolia Energy in the completion of the Mechanical Electrical, BMS and automated control applications of the Ichthy’s Gas Facility after the previously engaged contractor went into liquidation. The operation’s facility of the gas plant consisted of a range of diverse buildings, including a warehouse, hazardous chemical area, cafeteria, research and development area, laboratories and the gas plant’s main control room.
Hail Creek Industrial Area Upgrade
CE Group was engaged to perform 3 separate projects forming a major industrial upgrade at Hail Creek Mine, 120 kilometres inland from Mackay, Queensland.
The Hail Creek IAU – Warehouse project involved the supply, installation, testing and commissioning of electrical works for the 2,750m2 warehouse at Hail Creek Mine.
This project included the supply and installation of high bay lighting to suit task and racking requirements, office area lighting and the facility’s general power requirements. CE Group designed, manufactured and installed the Main Distribution Board (DB100) for the Warehouse. CE Groups scope of work included the supply and installation of several 25m Area Lighting Towers, including the associated civil works and the extensive power supply run to the Warehouse.